A farmer from Wadena, Sask., wants SaskPower to reconsider the route for a proposed three-phase power line that will affect his operation.
Chad Haskey said the new Viterra facility at Wadena requires the service, but the corporation has chosen an indirect route that divides his farm and puts his plans for an airstrip in jeopardy.
He said there is a better route.
“The only reason they’re not going the direct, shorter route is because the line would not go down an all-season road,” he said.
Read Also

Agriculture ministers agree to AgriStability changes
federal government proposed several months ago to increase the compensation rate from 80 to 90 per cent and double the maximum payment from $3 million to $6 million
The route past his house is on a better road but could place his employees in jeopardy because it would intersect where equipment is moved and set up.
He owns the property on both sides of the road.
“We come out our driveway across the road and set up equipment,” Haskey said.
The poles for a three-phase line are taller than others but are within the road allowance 33 feet from the centre of the road. He said combine headers are up to 45 feet wide and the poles could make turning difficult.
Haskey planned the airstrip for chemical application as well as a bin yard on the affected property.
“I’m not trying to hold back progress, but there are other options,” he said.
A SaskPower spokesperson said the corporation is meeting all applicable regulations and requires favourable topography and foundation conditions for its lines.
“We do try to minimize agriculture, environmental, social and other impacts such as the land use,” Leanne Persicke said.
“We minimize the economic impact such as construction costs, maintenance and operations from SaskPower’s perspective.”